Bridges Projects

PM CTRL stands for schedule-driven project controlling for complex bridge projects. We develop and maintain robust schedules for the client and project organization, monitor critical paths, and ensure compliance with possession windows and key milestones.

Ringbahnbrücke (Autobahndreieck Funkturm), Berlin — Photo: Kasa Fue, Wikimedia Commons, CC BY-SA 4.0; https://creativecommons.org/licenses/by-sa/4.0/

Ringbahnbrücke, Autobahndreieck Funkturm in Berlin

  • Type: Motorway Bridge
  • Role: Schedule Control, Risk Management (PM CTRL)
  • Investor: DEGES
  • Client: Zetcon Ingenieure GmbH
  • Phase: Planning & Execution
  • Timeframe: 2025 - 2027
  • Construction Volume: approx. 80€ million
Read more
Photo: Leonhard Lenz (CC0 1.0)

Westendbrücke, A100 – Berlin

  • Type: Motorway Bridge
  • Role: Schedule Control, Risk Management (PM CTRL)
  • Investor: DEGES
  • Client: Zetcon Ingenieure GmbH
  • Phase: Planning & Execution
  • Timeframe: 2025 - 2027
  • Construction Volume: approx. 50€ million
Read more

Filstal Bridge, part of the Wendlingen–Ulm high-speed rail line (Stuttgart 21 programme)

  • Type: Railway Bridge, ICE High Speed
  • Role: Project Management / Schedule & Cost Controlling (employed role)
  • Employer: Deutsche Bahn AG
  • Phase: Planning & Execution
  • Timeframe: 2016–2023
  • Construction Volume: approx. 200€ million
Read more

EÜ RIN 01, a part of the Megaproject: A100 – 16th Construction Phase – Berlin

  • Type: Railway Bridge, S-Bahn
  • Role: Project Controls / Project Management
  • Investor: Autobahn des Bundes GmbH
  • Client: KREBS+KIEFER Ingenieure GmbH
  • Phase: Execution
  • Timeframe: 2022–2025
  • Construction Volume: approx. 30€ million
Read more